Designer, builder and equipment suppliers put every new yacht through its paces in a formal and rigorous programme of sailing trials.
ROYAL HUISMAN DO SHIPYARD
Testing Program ACHARNE
June 1 Energysystems DC Supply,Measuring, Batteries
June 2 Energysystems DC Tank Testing,Measuring
Fuel Emergency connection trim pump
June 3 Stepping the mast Measuring + protection
Generator diesel Cooling water + exhausts
System
June 4 Trimming the mast
Generator Adjustment with water
Resistance
June 5 Energysystems AC Supply, parallel operation,
Measuring
Converter 50-60 Hz, Lighting
110V AC - 24V DC
June 9 Ventilation engine room
+ air treatment Generator room
Websto
Cabins and the rest of the ship
Audio/video/TV B + H antenna system
June 10 Charging systems measuring
(victron) Battery chargers
June 11 Electr.hydr.(Lewmar) Winches
Airconditioning H+H installation, 3x self
cont. Airco unit
208 v heating
June 12 Main engine (2x) Operation (Webco), Alternator
&15 140 Amp Measuring+Protection
Electr.Hydr. Rondal Marquip, 2x hundested pitch
Setting
Navtec hydraulics Bowthruster (up/down,
steering seat foldable hatch
accommodation, ladder
June 16 Electr.Hydr.Transmark Centre board, Aft cetre
&17 board, measuring
Bowthruster
June 18 Fresh water Shore connection, boiler , 2x
Draincock boiler, 1x cooler,
2x Ice maker, whirlpool,
watermaker, 2x sterilizer, 2x
water pump, 1x circulation
pump, 2x circulation pump for
generator heating
Mineral water pump
Winches Lewmar
June 19 Deckwash
Bilge Alarm
Pumps
Navigation B&G
Testing the deck
For leakage hatches, windows, etc.
June 19 Elec.hydr.
Sanguinetti gangway
Accommodation ladder
Steering system Tjenford
June 20 Pneumatic 2 compressors
Windows
Sliding door
Communication Sailtron, Ina, Intercom SNC
Jube 22 Cooling+freezing 2x freezer, 4x cooler, 1x
wine vault
Communication
June 23 Anchor
Communication Ina
Navigation Sailtron
Sump Pumps, measuring+alarm
June 24 Toilet system
Holding system pumps, measuring+alarm
Alarm system Burglar, windows/hatches
Closed video system
June 25 Galley equipment 2x dishwasher, fan hood, steak
grill, cooking plates, 2x hot
air oven, microwave, trash
compactor, 2x webasto
disposer, 2x washing machine,
4x dryer, 6x trouser press,
diving compressor.
June 26 safety equipment,spare parts, computer, mast
from the ship.
June 27 trails to Urk, testing
the main engines on the
IJsseleer, with Wizemann
June 29 stepping, trimming and
connecting the mast
June 30 hoisting+furling the sails
Testing the mast systems
July 1 trials on the IJsselmeer
Autopilot
July 2 sailing to IJmuiden calibrating the compass,
setting the log
July 3/9 Seatrials+sailing
Back to Urk, upholstery
etc
On board, finishing,
Sludge system, engine:
Changing oil, finishing
provisioning, bunkering etc
July 10 clearance +delivery 25.07.1987